电缆槽作业施工要求 |
添加时间:2018/6/30 17:49:43 浏览次数: |
电缆槽作业施工要求 Construction requirements of cable grooves 施工准备 Construction preparation 施工前对振捣平台等设备的运转情况进行检查,对施工人员的岗位资格进行核实。运至预制现场的砂、碎石、水泥、钢筋等原材料要进行抽样检验。施工场地及电缆槽成品存放场地建设完成。 Before construction, check the operation status of the vibrating platform and other equipment, and verify the qualification of the construction personnel. Raw materials such as sand, gravel, cement, steel bar and so on should be sampled for inspection. Construction site and cable slot product storage site construction completed. 施工工艺 construction technology 1、钢筋加工 1. Reinforcement processing 按设计施工图《铁路路基电缆槽》图号:通路(2010)8041的设计要求对进场合格的钢筋进行下料加工。并对下料的钢筋尺寸、规格验收,合格后方可使用。 According to design and construction plan "railway subgrade cable trench" figure No.: passage (2010) 8041 design requirements for incoming qualified steel bar processing. The size and specification of the rebar should be checked and accepted before being qualified. 2、模板加工 2, template processing 根据设计施工图《铁路路基电缆槽》图号:通路(2010)8041的电缆槽结构尺寸形式及现场施工用的电缆槽形式加工电缆槽硬塑料定型模具。电缆槽模具进场验收合格后方可使用,在使用过程中随时检查模具是否损坏,如有损坏清除淘汰。 According to the design and construction drawing "railway subgrade cable groove" figure number: the structure and size form of the channel (2010) 8041 cable groove and the cable groove in the field construction used for the cable groove hard plastic molding mold. The cable slot mold can be used before entering the field. If it is damaged during the use process, it will be eliminated if there is any damage. 3、钢筋安装 3. Installation of steel bar 电缆槽钢筋在钢筋加工场地绑扎完成(模外绑扎),电缆槽模具进场经验收合格后并清理干净,脱模剂涂刷均匀后。将电缆槽钢筋整体装入电缆槽模具中,并调整保护层间距直至满足设计及规范要求。 The cable groove bar is tied up in the processing site of the steel bar (outside the mold binding). The cable groove dies are qualified after acceptance and cleaned up, and the demoulding agent is evenly painted. The cable groove reinforcement is integrated into the cable slot mold, and the spacing between the protective layers is adjusted until the design and specification requirements are met. 4、混凝土浇筑 4, concrete pouring 电缆槽钢筋安装完成后,经质检工程师及监理验收合格后,浇筑混凝土。混凝土采用现场拌合的方式,振捣采用平板振捣器制作的振动台振捣,一般振捣时间控制在3-4min(根据现场实际可适当调整),不得过振。混凝土入模具分三层入模振捣,保证电缆槽内实外光。混凝土外露模具部分采用人工抹光压实。 After installation of cable groove reinforcement, concrete will be poured after quality inspection engineer and supervisor are qualified. The concrete adopts the way of field mixing, vibrate using the vibration table made by plate vibrator, the general vibration time is controlled in 3-4min (according to the actual field actual adjustment), no vibration. The concrete into the mold is divided into three layers into the mold to ensure that the inside and outside light of the cable trench is ensured. The concrete exposed mold part is artificially smoothed and compacted. 5、拆模养护 5. Mold maintenance 预制电缆槽混凝土拆模时间一般控制在混凝土强度达到2.5MPa以上。拆模后对电缆槽初次验收,对于完整无损的电缆槽加强养护,养护方式采用两种方式,一种是自然养护。采用土工膜或草袋覆盖洒水保湿的方式。这种方式适用于温度较高时。第二种方式采用蒸汽养护,这种方式适用于冬季施工的养护。两种养护方式的养护时间都不少于7天。 The concrete stripping time of precast cable trays is generally controlled by concrete strength up to 2.5MPa. After the initial acceptance of the cable trench after the removal of the mould, there are two ways to strengthen the maintenance of the cable trough, namely, the natural maintenance. Use geomembrane or straw bag to cover the way of watering and moisturizing. This method is suitable for high temperature. The second way is steam curing, which is suitable for maintenance in winter construction. The curing time of two curing methods is not less than 7 days. |
上一页 电缆槽盖板模具 |
下一页 电缆槽模具的保养 |
Copyright © 技术支持:遨游网络