返回首页

保定电缆槽模具厂

本站导航

新闻动态

当前位置:网站首页 > 新闻动态 > 详细信息
电缆敷设施工顺序及部署安排
添加时间:2021/8/3 15:54:02     浏览次数:
电缆敷设施工顺序及部署安排
Construction sequence and arrangement of cable laying
(一)施工准备
(1) construction preparation
1、技术准备
1. Technical preparation
1·1认真熟识、审核施工图纸,领会设计意图,严格按照图纸要求进行电缆敷设;
1.1 Be familiar with and examine the construction drawings carefully, understand the design intentions, and lay the cables strictly according to the requirements of the drawings.
1·2电缆必须报经监理进行严格的检验,合格后方可施工;
1. 2 cable must be reported to be strictly tested by supervision and qualified before construction.
1·3针对工程情况,对施工班组进行技术交底;
1. 3, in accordance with the engineering situation, the technical team of the construction team was provided.
1·4根据工程实际情况划分施工流水段,并以此为依据检查井钢模具 隔离墩模具 隔离墩钢模具 流水槽模具 U型槽模具 螺杆启闭机 卷扬式启闭机 铜雕佛像 确定劳动力及材料需用量及施工人数;
1.4 According to the actual situation of the project, divide the construction flow section, and determine the amount of labor and materials needed and the number of construction workers.
1·5根据工程的实际需要培训操作工人,特殊工种操作人员必须持证上岗。
1. 5 training operators according to the actual needs of the project. Special workers must be certified.
2、机械、工具准备
2. Machinery and tools preparation
2·1电缆敷设机、电缆支架及电缆轴、电缆滚轮、吊链、滑轮、尼龙绳、钢丝绳;
2.1 Cable laying machine, cable bracket and cable shaft, cable roller, chain, pulley, nylon rope, wire rope
上一页  水沟盖板模具的材质性能  
下一页  水沟电缆槽移动模具应用情况
  • 关于我们
  • 新闻动态
  • 案例展示
  • 网上订单
  • 联系我们
  • 产品分类1
  • 产品分类2
  • 产品分类3

Copyright © 技术支持:遨游网络

  • 联系我们
  • 网上订单
  • 工程案例
  • 本站导航

搜索

  • 关于我们
  • 新闻动态
  • 案例展示
  • 网上订单
  • 联系我们
  • 产品分类1
  • 产品分类2
  • 产品分类3